Current Projects

      Blackburn Elementary

      • Construction Update 9/1/24

        Blackburn Elementary

        CM Agreement with A. D. Morgan, Inc. ($36,404,396)
        A/E Agreement with Wannemacher Jensen Architects ($1,727,211)

          

         


        Budget

        $40,787,200

        As of 9/1/24, Expended $13,996,143
        As of 9/1/24, Sales Tax Savings $264,963

         


        Funding Source

        COPS

         


        Scope of Work

        Replace Existing Building 1 Admin, Media, Cafeteria, Primary Classrooms; Complete renovation of existing HVAC, Plumbing, Electric, Technology, Building Envelope, & Interior Finishes; Improve on-site traffic queuing

        New Building 1: Under Construction
        Existing Building 8: Under Renovation; New HVAC units & utilities installed

         


        Schedule

        Project Design Start: August 2022

        Construction Start: August 2023

        Substantial Completion: Phased; Final completion November 2025

        37% Complete

        As of 9/1/24, Project On Schedule

         


        Project Director

        Jeffery Medwetz

         

      Haile Middle

      • Construction Update 9/1/24

        Haile Middle

        CM Agreement with Halfacre Construction Company ($36,781,249)
        A/E Agreement with Long and Associates ($2,059,250)

          

         


        Budget

        $46,204,358

        As of 9/1/24, Expended $28,590,914
        As of 9/1/24, Sales Tax Savings $268,140

         


        Funding Source

        COPS and Impact Fees

         


        Scope of Work

        New Building 8 Ten Classroom Addition; Complete renovation of existing HVAC, Plumbing, Electric, Technology, Building Envelope, & Interior Finishes

        Current Status: Completing Punch List  

         


        Schedule

        Project Design Start: July 2022
        Construction Start: June 2023
        Substantial Completion Buildings 1 – 8: August 2024
        Locker Room Renovation: Summer 2025

        82% Complete

        As of 9/1/24, Project On Schedule

         


        Project Director

        Jeffery Medwetz

         

      Oneco Elementary

      • Construction Update 9/1/24

        Oneco Elementary

        CM Agreement with Charles Perry Partners, Inc. ($34,737,302)
        A/E Agreement with Zyscovich Architects ($1,678,768)

          

         


        Budget

        $39,514,846

        As of 9/1/24, Expended $11,308,062
        As of 9/1/24, Sales Tax Savings $294,142

         


        Funding Source

        COPS

         


        Scope of Work

        New Building 1 Media and Admin; Complete renovation of existing HVAC, Plumbing, Electric, Technology, & Building Envelope systems; Improve on-site traffic queuing

        New Building 1: Under Construction
        Existing Building 3: Under Renovation
        Existing Building 6: Under Renovation 

         


        Schedule

        Project Design Start: August 2022
        Construction Start: September 2023
        Substantial Completion: Phased; Final completion April 2026

        16% Complete

        As of 9/1/24, Project On Schedule

         


        Project Director

        Jeffery Medwetz

         

      Tara Elementary

      • Construction Update 9/1/24

        Tara Elementary

        CM Amendment 5, Guaranteed Max Price with Creative Contractors, Inc. ($31,402,356)
        A/E Amendment 2, with Sweet Sparkman Architects, Inc. ($2,154,751)

          

         


        Budget

        $35,259,423

        As of 9/1/24, Expended $13,987,209
        As of 9/1/24, Sales Tax Savings $286,415

         


        Funding Source

        COPS

         


        Scope of Work

        DOE Castaldi Analysis – Renovation Only Approved

        Campus-wide renovation and required site improvements with Four (4) Classroom building addition, including roof replacement, security upgrade, and removal of portables

        Building 1 Renovation: 90% complete and occupied

        Building 2 Renovation: Selective demolition in progress

         


        Schedule

        Project Design Start: July 2022

        Construction Start: June 2023

        Substantial Completion: August 2025

        40% Complete

        As of 9/1/24, Project Phase 3 delayed, Remaining Phases On Schedule

         


        Project Director

        Michelle Begué