Construction Services
Page Navigation
Current Projects
-
The Department of Construction Services (DCS) is working on these Current Projects, including building new schools.
Blackburn Elementary
-
Construction Update 9/1/24
Blackburn Elementary
CM Agreement with A. D. Morgan, Inc. ($36,404,396)
A/E Agreement with Wannemacher Jensen Architects ($1,727,211)
Budget
$40,787,200
As of 9/1/24, Expended $13,996,143
As of 9/1/24, Sales Tax Savings $264,963
Funding Source
COPS
Scope of Work
Replace Existing Building 1 Admin, Media, Cafeteria, Primary Classrooms; Complete renovation of existing HVAC, Plumbing, Electric, Technology, Building Envelope, & Interior Finishes; Improve on-site traffic queuing
New Building 1: Under Construction
Existing Building 8: Under Renovation; New HVAC units & utilities installed
Schedule
Project Design Start: August 2022
Construction Start: August 2023
Substantial Completion: Phased; Final completion November 2025
37% Complete
As of 9/1/24, Project On Schedule
Project Director
Jeffery Medwetz
Haile Middle
-
Construction Update 9/1/24
Haile Middle
CM Agreement with Halfacre Construction Company ($36,781,249)
A/E Agreement with Long and Associates ($2,059,250)
Budget
$46,204,358
As of 9/1/24, Expended $28,590,914
As of 9/1/24, Sales Tax Savings $268,140
Funding Source
COPS and Impact Fees
Scope of Work
New Building 8 Ten Classroom Addition; Complete renovation of existing HVAC, Plumbing, Electric, Technology, Building Envelope, & Interior Finishes
Current Status: Completing Punch List
Schedule
Project Design Start: July 2022
Construction Start: June 2023
Substantial Completion Buildings 1 – 8: August 2024
Locker Room Renovation: Summer 202582% Complete
As of 9/1/24, Project On Schedule
Project Director
Jeffery Medwetz
Oneco Elementary
-
Construction Update 9/1/24
Oneco Elementary
CM Agreement with Charles Perry Partners, Inc. ($34,737,302)
A/E Agreement with Zyscovich Architects ($1,678,768)
Budget
$39,514,846
As of 9/1/24, Expended $11,308,062
As of 9/1/24, Sales Tax Savings $294,142
Funding Source
COPS
Scope of Work
New Building 1 Media and Admin; Complete renovation of existing HVAC, Plumbing, Electric, Technology, & Building Envelope systems; Improve on-site traffic queuing
New Building 1: Under Construction
Existing Building 3: Under Renovation
Existing Building 6: Under Renovation
Schedule
Project Design Start: August 2022
Construction Start: September 2023
Substantial Completion: Phased; Final completion April 202616% Complete
As of 9/1/24, Project On Schedule
Project Director
Jeffery Medwetz
Tara Elementary
-
Construction Update 9/1/24
Tara Elementary
CM Amendment 5, Guaranteed Max Price with Creative Contractors, Inc. ($31,402,356)
A/E Amendment 2, with Sweet Sparkman Architects, Inc. ($2,154,751)
Budget
$35,259,423
As of 9/1/24, Expended $13,987,209
As of 9/1/24, Sales Tax Savings $286,415
Funding Source
COPS
Scope of Work
DOE Castaldi Analysis – Renovation Only Approved
Campus-wide renovation and required site improvements with Four (4) Classroom building addition, including roof replacement, security upgrade, and removal of portables
Building 1 Renovation: 90% complete and occupied
Building 2 Renovation: Selective demolition in progress
Schedule
Project Design Start: July 2022
Construction Start: June 2023
Substantial Completion: August 2025
40% Complete
As of 9/1/24, Project Phase 3 delayed, Remaining Phases On Schedule
Project Director
Michelle Begué