Construction Update 2/14/25
Rye Ranch Elementary
Budget
$75,000,000.00
Funding Source
COPS 2025
Scope of Work
Two-story prototype new construction designed to serve 969 students in grades K-5.
Schedule
Project Design Start: November 2024
Construction Start: March 2025
Substantial Completion: June 2026
Design in Progress
As of 2/14/25, Project On Schedule
Project Director
Reginald Goff / Jerry Varghese